RUNFOLD AREA A RESTORATION

At last Pope's move on to the Restoration of Area A at the Suez site now that ecology work is complete within this area.

The pressure was now firmly on to get the site restored, seeded and completed before the weather turned.
The works were unlike a normal restoration project where soils are just placed.
the works consisted of loose soils placement procedure after ripping of the ground to 400mm with our D6T LGP dozer. The soils had to be excavated from  various stockpiles around the site and placed to various thicknesses for tree planting and seeding.
The works also consisted of excavating surface water lagoons and installing extremely wide topsoil lined surface water ditches. Our Service engineer was required to fabricate a bucket to suit specification.
The works were completed with only days to spare before the weather broke for the winter.


“The pressure was now firmly on to get the site restored, seeded and completed”

Red Materials Ltd Testimonial 2018

“All work has been carried out in accordance with an approved CQA Plan and has been undertaken to the highest standards.

Craig Pope and his team are knowledgeable, approachable and have an excellent attitude towards Health & Safety

I would strongly recommend the services of Pope Plant Ltd.”

Find out more about

LANDFILL

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Wednesday October 6th, 2021
Pope Plant LTD
Another successful project completed at Bellhouse Landfill.  Showing Pope Plant workforce doing what they do best - working as a team - working WITH our client not just FOR them.

www.popeplant.co.uk

Another successful project completed at Bellhouse Landfill. Showing Pope Plant workforce doing what they do best - working as a team - 'working WITH our client not just FOR them'.

www.popeplant.co.uk
... See MoreSee Less

Comment on Facebook

Tidy job, always enjoyed doing the landfill cells 👍

Thursday June 17th, 2021
Pope Plant LTD
2nd 2014 Volvo A25F added to the fleet in the past 3 months

2nd 2014 Volvo A25F added to the fleet in the past 3 months ... See MoreSee Less

Tuesday June 8th, 2021
Pope Plant LTD
New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today

New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today ... See MoreSee Less