Rock Buttress

Mineral extraction and restoration works were completed at Tapwood during 2015. The pumping system was de-commissioned to allow the quarry to naturally flood for possible use as a recreation area for the land owner to utilise.

During early 2016, various areas of quarry side walls began to fail and collapse due to soft seams of sand being present.

One particular area began to course concern for the Geologists so design ideas were passed around over the coming months until a decision was made to design and build a protection rock buttress.

Pope Plant Ltd tendered and were awarded the works, which started in October 2016.

The works consisted of the importation of over 20โ€™000 tons of Kent ragstone from another Hanson owned Quarry operated by the Gallagher Group.

The site had access restrictions which limited the importation rate and working area. The rock was tipped to stockpile and reloaded by Pope excavator in to a 30 ton ADT to transport to the failed area. The rock was placed into deep water by another excavator to construct a safe causeway to the proposed buttress area. Once the causeway was complete, the buttress was formed by a larger 30 ton excavator carefully placing the rock to avoid any further disturbance to the surrounding area.

The whole works from start to finish required constant monitoring for any change in conditions with revised RAMS implemented by Pope staff as required.

The works were completed within the given timescales and within budget.

 

“The works consisted of the importation of over 20โ€™000 tons of Kent ragstone from another Hanson owned Quarry operated by the Gallagher Group.”

Description of the image

HANSON-REIG-M-UTTLEY 2017

 

“I would not hesitate to invite Pope Plant ltd to bid for future earthworks projects with Hanson, and
recommend them to any prospective clients.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons

Friday June 12th, 2020

Pope Plant LTD
Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included 
Ground Remediation 
Cut/Fill earthworks 
Cement Stabilisation carried out by third party
Aggregate placement 
Contract variations 
Additional works for landowner

Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included
Ground Remediation
Cut/Fill earthworks
Cement Stabilisation carried out by third party
Aggregate placement
Contract variations
Additional works for landowner
... See MoreSee Less

Friday May 15th, 2020

Pope Plant LTD
At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Letโ€™s cautiously and safely as possible get the economy going again which is what construction does๐Ÿ‘

At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Letโ€™s cautiously and safely as possible get the economy going again which is what construction does๐Ÿ‘
... See MoreSee Less

Comment on Facebook

When are you heading to Colchester mate.๐Ÿ‘

Keep the tracks turning mate ๐Ÿ‘๐Ÿ‘๐Ÿ‘๐Ÿ‘๐Ÿ‘

Thursday March 12th, 2020

Pope Plant LTD
Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.
Another client happy๐Ÿ˜€

Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.
Another client happy๐Ÿ˜€
... See MoreSee Less