GCL Capping

Following straight on from the completed contract at Greatness, Pope Plant Ltd mobilised to the Bellhouse site in Colchester.

An area had now been completed with waste to finish level next to the circa 40’000m2 of permanent GCL capping, Pope installed in 2015.

The new area required 25’000m2 of regulation material to be place, followed by GCL installation and 300mm protection layer of soil placement for stockpile.

The works were carried out under the supervision of Terra Consult CQA engineer during the summer months with very little interruption from adverse weather.

The works were completed on time and within budget.

 

“The works were carried out under the supervision of Terra Consult CQA engineer during the summer months with very little interruption from adverse weather.”

Description of the image

CORY-TR-MARTIN 2013

 

“I found Craig and his plant operators very professional.  They carried out our projects to a very high standard, within timescales and budgets.  We had good working relations with Craig’s staff.  The plant is kept to a high standard.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons