GCL Capping

Following straight on from the completed contract at Greatness, Pope Plant Ltd mobilised to the Bellhouse site in Colchester.

An area had now been completed with waste to finish level next to the circa 40’000m2 of permanent GCL capping, Pope installed in 2015.

The new area required 25’000m2 of regulation material to be place, followed by GCL installation and 300mm protection layer of soil placement for stockpile.

The works were carried out under the supervision of Terra Consult CQA engineer during the summer months with very little interruption from adverse weather.

The works were completed on time and within budget.

 

“The works were carried out under the supervision of Terra Consult CQA engineer during the summer months with very little interruption from adverse weather.”

Description of the image

CORY-TR-MARTIN 2013

 

“I found Craig and his plant operators very professional.  They carried out our projects to a very high standard, within timescales and budgets.  We had good working relations with Craig’s staff.  The plant is kept to a high standard.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons

Friday June 12th, 2020

Pope Plant LTD
Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included 
Ground Remediation 
Cut/Fill earthworks 
Cement Stabilisation carried out by third party
Aggregate placement 
Contract variations 
Additional works for landowner

Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included
Ground Remediation
Cut/Fill earthworks
Cement Stabilisation carried out by third party
Aggregate placement
Contract variations
Additional works for landowner
... See MoreSee Less

Friday May 15th, 2020

Pope Plant LTD
At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Let’s cautiously and safely as possible get the economy going again which is what construction does👍

At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Let’s cautiously and safely as possible get the economy going again which is what construction does👍
... See MoreSee Less

Comment on Facebook

When are you heading to Colchester mate.👍

Keep the tracks turning mate 👍👍👍👍👍

Thursday March 12th, 2020

Pope Plant LTD
Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.
Another client happy😀

Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.
Another client happy😀
... See MoreSee Less