PHASED CAPPING

Redhill Landfill Southern Area Phased Capping involved the excavation of approximately 110’000m3 of existing membrane capping and soils on a phase by phase basis.

The soils were hauled and placed to temporary stockpiles for later use within the works. The old membrane cap was disposed of to the active landfill.

The client then filled the newly created void with waste from various sources. Upon completetion of filling the area was then made available for re-capping.

Preparation of waste formation was required to receive waste regulation layer. Once regulation material was placed a 0.5mm LLDPE membrane was installed using the lap and lay method. A Geotextile was then placed over the membrane for protection. Conformance testing was completed by a UKAS accredited laboratory.

When the permanent capping was complete, soils were then excavated, hauled and placed to a depth of 1 metre to restore the area.

Finally a surface water management system was installed.

“The old membrane cap was disposed of to the active landfill”


                  

BWSL-A-COLEMAN 2011

 

“Any future employer of this company will soon come to note their commitment and ability to complete a project within budget and without undue compensation events.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 19th, 2022
Pope Plant LTD
Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed

Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed ... See MoreSee Less

Comment on Facebook

well done mate great achievement, good on you for needing the extra building. glad your busy

Hi Craig, is dad still about

Saturday March 19th, 2022
Pope Plant LTD
Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between

Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between
... See MoreSee Less

Wednesday February 9th, 2022
Pope Plant LTD
Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced

Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced ... See MoreSee Less