PHASED CAPPING

Redhill Landfill Southern Area Phased Capping involved the excavation of approximately 110’000m3 of existing membrane capping and soils on a phase by phase basis.

The soils were hauled and placed to temporary stockpiles for later use within the works. The old membrane cap was disposed of to the active landfill.

The client then filled the newly created void with waste from various sources. Upon completetion of filling the area was then made available for re-capping.

Preparation of waste formation was required to receive waste regulation layer. Once regulation material was placed a 0.5mm LLDPE membrane was installed using the lap and lay method. A Geotextile was then placed over the membrane for protection. Conformance testing was completed by a UKAS accredited laboratory.

When the permanent capping was complete, soils were then excavated, hauled and placed to a depth of 1 metre to restore the area.

Finally a surface water management system was installed.

“The old membrane cap was disposed of to the active landfill”


                  

BWSL-A-COLEMAN 2011

 

“Any future employer of this company will soon come to note their commitment and ability to complete a project within budget and without undue compensation events.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Wednesday October 6th, 2021
Pope Plant LTD
Another successful project completed at Bellhouse Landfill.  Showing Pope Plant workforce doing what they do best - working as a team - working WITH our client not just FOR them.

www.popeplant.co.uk

Another successful project completed at Bellhouse Landfill. Showing Pope Plant workforce doing what they do best - working as a team - 'working WITH our client not just FOR them'.

www.popeplant.co.uk
... See MoreSee Less

Comment on Facebook

Tidy job, always enjoyed doing the landfill cells 👍

Thursday June 17th, 2021
Pope Plant LTD
2nd 2014 Volvo A25F added to the fleet in the past 3 months

2nd 2014 Volvo A25F added to the fleet in the past 3 months ... See MoreSee Less

Tuesday June 8th, 2021
Pope Plant LTD
New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today

New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today ... See MoreSee Less