CAPPING AND SURFACE WATER WORKS

On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.

Whilst Biffa was behind with the input of waste to NE quadrant, it was decided by all parties that the work to construct surface water lagoon would begin then follow on to the capping works later upon completion of filling operation.

There was 25’000m3 of clay excavated, hauled and placed on a long haul from one side of site to the other to construct lagoon. This was removed from previously placed stockpile in the rented farmer’s field.

The lagoon was 95% complete only, due to the discharge point to Combe Haven not being granted permission in time by the EA.

Waste filling to NE Quadrant was complete mid November, some 8 weeks behind schedule due to unforeseen reduced inputs. This led to only 8’000m2 of LLDPE welded membrane being deployed by Pope Plant nominated sub-contractor before the worse winter on record stopped the works.

Pope Plant Ltd are due back to site Spring 2014 to complete the remaining works.

“On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.”


                  

BIFFA-M-STEPHENSON 2011

 

“I have always found working with Pope Plant to be easy and that they are a dependable contractor with high levels of workmanship.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 19th, 2022
Pope Plant LTD
Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed

Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed ... See MoreSee Less

Comment on Facebook

well done mate great achievement, good on you for needing the extra building. glad your busy

Hi Craig, is dad still about

Saturday March 19th, 2022
Pope Plant LTD
Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between

Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between
... See MoreSee Less

Wednesday February 9th, 2022
Pope Plant LTD
Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced

Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced ... See MoreSee Less