CAPPING AND SURFACE WATER WORKS

On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.

Whilst Biffa was behind with the input of waste to NE quadrant, it was decided by all parties that the work to construct surface water lagoon would begin then follow on to the capping works later upon completion of filling operation.

There was 25โ€™000m3 of clay excavated, hauled and placed on a long haul from one side of site to the other to construct lagoon. This was removed from previously placed stockpile in the rented farmerโ€™s field.

The lagoon was 95% complete only, due to the discharge point to Combe Haven not being granted permission in time by the EA.

Waste filling to NE Quadrant was complete mid November, some 8 weeks behind schedule due to unforeseen reduced inputs. This led to only 8’000m2 of LLDPE welded membrane being deployed by Pope Plant nominated sub-contractor before the worse winter on record stopped the works.

Pope Plant Ltd are due back to site Spring 2014 to complete the remaining works.

“On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.”


                  

BIFFA-M-STEPHENSON 2011

 

“I have always found working with Pope Plant to be easy and that they are a dependable contractor with high levels of workmanship.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons

Friday September 18th, 2020

Pope Plant LTD
Highlighting the extent of this Cell build excavation with our 35t Komatsu excavator just visible in the bottom ๐Ÿ‘

Highlighting the extent of this Cell build excavation with our 35t Komatsu excavator just visible in the bottom ๐Ÿ‘ ... See MoreSee Less

Friday September 18th, 2020

Pope Plant LTD
Ever increasing landfill Cell
Adding an awkward chunk of clay engineering whilst the sun shines๐ŸŒž
One of the largest, if not the largest landfill Cells constructed in the South East this year.
Cell 9 almost complete ๐Ÿ‘Œ

Ever increasing landfill Cell
Adding an awkward chunk of clay engineering whilst the sun shines๐ŸŒž
One of the largest, if not the largest landfill Cells constructed in the South East this year.
Cell 9 almost complete ๐Ÿ‘Œ
... See MoreSee Less

Comment on Facebook

Looks great Craig,Cracking job mate.๐Ÿ‘

View more comments

Thursday August 6th, 2020

Pope Plant LTD
Finally after overcoming massive ground water problems , variations to the contract and unforeseen issues!
We finally achieved formation and began clay engineering works this week on one of the largest, if not the largest, landfill Cells under construction in the South of England
Onwards and upwards ๐Ÿ‘

Finally after overcoming massive ground water problems , variations to the contract and unforeseen issues!
We finally achieved formation and began clay engineering works this week on one of the largest, if not the largest, landfill Cells under construction in the South of England
Onwards and upwards ๐Ÿ‘
... See MoreSee Less