HANSON TICE MEADOW - 2019

The work was a very small but important contract for the local community to enjoy nature at its finest on a previously restored Hanson Quarry in Farnham.

A tricky 30ft bird hide was carried nearly a mile with one excavator having to track backwards the full distance supervised and guided by local safety inducted volunteers
Once this was carefully placed to the delight of the locals, further ancillary works were carried out carefully and respectfully to the local surroundings.

“WE ALWAYS WORK WITH OUR CLIENTS NOT JUST FOR THEM” Craig Pope 2019


HANSON-REIG-M-UTTLEY 2017

 

“I would not hesitate to invite Pope Plant ltd to bid for future earthworks projects with Hanson, and
recommend them to any prospective clients.”

Find out more about

EARTHWORKS

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons

Friday June 12th, 2020

Pope Plant LTD
Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included 
Ground Remediation 
Cut/Fill earthworks 
Cement Stabilisation carried out by third party
Aggregate placement 
Contract variations 
Additional works for landowner

Lower Drayton AD Plant earthworks package completed today in 4 weeks meeting all deadlines and within budget
Included
Ground Remediation
Cut/Fill earthworks
Cement Stabilisation carried out by third party
Aggregate placement
Contract variations
Additional works for landowner
... See MoreSee Less

Friday May 15th, 2020

Pope Plant LTD
At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Letโ€™s cautiously and safely as possible get the economy going again which is what construction does๐Ÿ‘

At last we have some plant going out the gate to work on a new AD Plant project in the Midlands
New Covid procedures and policies are in place along with individual operator kits.
Letโ€™s cautiously and safely as possible get the economy going again which is what construction does๐Ÿ‘
... See MoreSee Less

Comment on Facebook

When are you heading to Colchester mate.๐Ÿ‘

Keep the tracks turning mate ๐Ÿ‘๐Ÿ‘๐Ÿ‘๐Ÿ‘๐Ÿ‘

Thursday March 12th, 2020

Pope Plant LTD
Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.
Another client happy๐Ÿ˜€

Our smallest excavator on the fleet had a busy day yesterday installing ducting and new electrical cable to the Jetty in a boat yard in Gravesend.
It was a race against time to beat the high Thames Spring tide.