Cell 8b construction and capping

After talks between Cory's and Pope Plant it was decided to start the works at Greatness.

After viewing the proposed works involved in the construction of Cell 8b, it was apparent that the build would prove challenging with the surrounding leachate levels and exposing the intercell bunds. Due to the close working relationship between Client and contractor, the works were awarded on a day work basis with all costs and works involved presented in daily journal format on a weekly basis for monitoring purpose.

The works involved :

  • Excavation of material from cell to restoration
  • Clay excavation to stockpile GCL installation
  • Clay stockpile to engineering
  • Installation of textile and aggregate drainage blanket + sump and monitoring points.
  • Installation and removal of pumping system during the works

In addition to the standard Cell and Capping works, selective excavation of materials were required along with the requirement to cross boundary fence into the Lafarge Tarmac Quarry to excavate and haul quality engineering clay to Cell 8b. Pope plant Ltd had to work closely with two clients adhering to both companies H&S regulations along with a third party earthworks contractor carrying out stripping works for Lafarge Tarmac. There were no issues reported regarding Health and Safety.

The works were complete even with inclement weather conditions hitting hard towards the end of contract.

Works were within the client budget and worked sufficiently on a day work basis.

Pope Plant Ltd are provisionally in line to start Cell 8c works working with Cory Environmental Ltd and Lafarge Tarmac, early spring 2015.


“The works were complete even with inclement weather conditions hitting hard towards the end of contract.”

CORY-M-HARLING 2011

 

“Pope Plant Ltd are continually asked back to tender as on site issues are dealt with effectively and fairly without any claims being submitted as Craig does NOT work on a claims basis.

The work is always carried out to a high standard on time and budget with a 100% Health and safety record. Furthermore Craig is who we always deal with takes ownership of the work and keeps us informed of issues which re always sorted to the best interest of all concerned.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 19th, 2022
Pope Plant LTD
Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed

Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed ... See MoreSee Less

Comment on Facebook

well done mate great achievement, good on you for needing the extra building. glad your busy

Hi Craig, is dad still about

Saturday March 19th, 2022
Pope Plant LTD
Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between

Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between
... See MoreSee Less

Wednesday February 9th, 2022
Pope Plant LTD
Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced

Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced ... See MoreSee Less