CELL ENGINEERING, CAPPING AND RESTORATION

Following on from Cell 8 works in 2012, Pope Plant ltd were awarded as principal contractor Cell 8b construction and engineering along with Cell 7 capping and restoration.

The works involved preparing previously installed regulation layer along with a further 10’000m2 placement of material. We exposed tie-in for the placement of 20’000m2 of GCL carried out by our team of installers and equipment. The work was supervised full time by client chosen consultant Egniol.

The GCL was then covered to a depth of 1m from the Cell 8b excavation material. The in-situ engineering clay was then shaped to fall to the lowest point so surface water could be controlled until summer 2014 when engineering would take place.

There were some remedial works undertaken to repair engineering clay batter slips during the winter of 2012.

A new haul road was constructed in preparation to receive waste inputs to Cell 7b without the need to go through the middle of Cell 8b.

The work was completed on time and budget during the summer months.

“Following on from Cell 8 works in 2012, Pope Plant ltd were awarded as principal contractor Cell 8b construction and engineering along with Cell 7 capping and restoration.”


                  

CORY-ALISTAIR-HOLL 2011

 

“A clear strength of Pope Plant is the close and direct management of all works by Craig Pope, who has consistently demonstrated the desire to complete works efficiently and cost effectively, even on occasion when unforeseen circumstances may occur.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 19th, 2022
Pope Plant LTD
Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed

Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed ... See MoreSee Less

Comment on Facebook

well done mate great achievement, good on you for needing the extra building. glad your busy

Hi Craig, is dad still about

Saturday March 19th, 2022
Pope Plant LTD
Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between

Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between
... See MoreSee Less

Wednesday February 9th, 2022
Pope Plant LTD
Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced

Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced ... See MoreSee Less