DOWNLAND - MANOR BARN CONTINUES - 2019

The continuation of engineering at Manor Barn Quarry

Cell 2 Side Wall Lift No.2
Cell 3 Base and Side Wall
Restoration of adjacent field upon removal of stockpile
Works commenced to extend the engineering on site to continue infilling of inert materials.
The works consisted of placing site derived and imported material in layers, rolled and tested to create large void space with the intention of getting through to Spring 2020.
An adjacent field used to stockpile site material when entrance road was constructed was ripped and restored back to farming once all material was used for engineering.

Pope Plant Ltd continue to supply Plant and Labour on a weekly basis for the day to day running of the site


DOWNLAND 2018

“The project team was led by Craig Pope, who was able to deliver the works professionally, on time and in a cost efficient manner. His hands on approach and clear understanding of the technical challenges meant that he was able to liaise effectively with us and to work competently to any directions he was given.

We have full confidence in Craig and his experienced team and would unreservedly recommend his services to anyone requiring similar works undertaken, particularly if there are technically challenging aspects to it.”

Find out more about

EARTHWORKS AND OPERATORS

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons

Friday September 18th, 2020

Pope Plant LTD
Highlighting the extent of this Cell build excavation with our 35t Komatsu excavator just visible in the bottom πŸ‘

Highlighting the extent of this Cell build excavation with our 35t Komatsu excavator just visible in the bottom πŸ‘ ... See MoreSee Less

Friday September 18th, 2020

Pope Plant LTD
Ever increasing landfill Cell
Adding an awkward chunk of clay engineering whilst the sun shines🌞
One of the largest, if not the largest landfill Cells constructed in the South East this year.
Cell 9 almost complete πŸ‘Œ

Ever increasing landfill Cell
Adding an awkward chunk of clay engineering whilst the sun shines🌞
One of the largest, if not the largest landfill Cells constructed in the South East this year.
Cell 9 almost complete πŸ‘Œ
... See MoreSee Less

Comment on Facebook

Looks great Craig,Cracking job mate.πŸ‘

View more comments

Thursday August 6th, 2020

Pope Plant LTD
Finally after overcoming massive ground water problems , variations to the contract and unforeseen issues!
We finally achieved formation and began clay engineering works this week on one of the largest, if not the largest, landfill Cells under construction in the South of England
Onwards and upwards πŸ‘

Finally after overcoming massive ground water problems , variations to the contract and unforeseen issues!
We finally achieved formation and began clay engineering works this week on one of the largest, if not the largest, landfill Cells under construction in the South of England
Onwards and upwards πŸ‘
... See MoreSee Less