REMOBILISATION TO COMPLETE WORKS

The same situation occurred as Welford in late 2012, where Colnbrook LFS final restoration was incomplete due to inclement weather conditions.

The same situation occurred as Welford in late 2012, where Colnbrook LFS final restoration was incomplete due to inclement weather conditions.

Pope Plant Ltd re-mobilised to complete the excavation, haul and place of 10’000m3 of subsoils and 24’000m3 of topsoil. Before work commenced the perimeter gas main required isolation and disconnection to obtain safe access to main stockpile. Our nominated sub-contractor carried out the disconnection and reposition under the

supervision of the internal Gas to energy team.

A perimeter bund and v-ditch was constructed at the front end of the site in order to deter any unwanted vehicle trespassing.

A new track was placed using site derived materials for the possible placement of further imported restoration materials subject to planning.

“Before work commenced the perimeter gas main required isolation and disconnection to obtain safe access to main stockpile. “


                  

BWSL-A-COLEMAN 2011

 

“Any future employer of this company will soon come to note their commitment and ability to complete a project within budget and without undue compensation events.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Wednesday October 6th, 2021
Pope Plant LTD
Another successful project completed at Bellhouse Landfill.  Showing Pope Plant workforce doing what they do best - working as a team - working WITH our client not just FOR them.

www.popeplant.co.uk

Another successful project completed at Bellhouse Landfill. Showing Pope Plant workforce doing what they do best - working as a team - 'working WITH our client not just FOR them'.

www.popeplant.co.uk
... See MoreSee Less

Comment on Facebook

Tidy job, always enjoyed doing the landfill cells 👍

Thursday June 17th, 2021
Pope Plant LTD
2nd 2014 Volvo A25F added to the fleet in the past 3 months

2nd 2014 Volvo A25F added to the fleet in the past 3 months ... See MoreSee Less

Tuesday June 8th, 2021
Pope Plant LTD
New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today

New MC1 Leica upgrade to one of our 21t Komatsu PC210LC-10 excavators today ... See MoreSee Less