BWSL REDHILL - 2018

Cell 8 Upper Engineered lift completion

As a late request Biffa Waste Services approached Pope Plant Ltd to seek the possibility of finishing an upper engineering lift left over from a previous contractor.

Due to the unexpected halt of restoration works with ecology issues on another site, Pope plant were in a position to proceed with these works with immediate effect which suited the client.

The works involved trimming formation, removing water and U/S material from the base in order to find tie-In, Clay Engineering, membrane and protection textile installation.

With help from a trusted sub-contractor previously used for material installation, the works were completed on time and within budget on a part price, part daywork basis.

BIFFA-M-STEPHENSON 2011

 

“I have always found working with Pope Plant to be easy and that they are a dependable contractor with high levels of workmanship.”

Find out more about

LANDFILL

Details