CELL ENGINEERING, CAPPING AND RESTORATION

Following on from Cell 8 works in 2012, Pope Plant ltd were awarded as principal contractor Cell 8b construction and engineering along with Cell 7 capping and restoration.

The works involved preparing previously installed regulation layer along with a further 10’000m2 placement of material. We exposed tie-in for the placement of 20’000m2 of GCL carried out by our team of installers and equipment. The work was supervised full time by client chosen consultant Egniol.

The GCL was then covered to a depth of 1m from the Cell 8b excavation material. The in-situ engineering clay was then shaped to fall to the lowest point so surface water could be controlled until summer 2014 when engineering would take place.

There were some remedial works undertaken to repair engineering clay batter slips during the winter of 2012.

A new haul road was constructed in preparation to receive waste inputs to Cell 7b without the need to go through the middle of Cell 8b.

The work was completed on time and budget during the summer months.

“Following on from Cell 8 works in 2012, Pope Plant ltd were awarded as principal contractor Cell 8b construction and engineering along with Cell 7 capping and restoration.”


                  

CORY-ALISTAIR-HOLL 2011

 

“A clear strength of Pope Plant is the close and direct management of all works by Craig Pope, who has consistently demonstrated the desire to complete works efficiently and cost effectively, even on occasion when unforeseen circumstances may occur.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less

Thursday April 25th, 2024
Pope Plant LTD
Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.

Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.
... See MoreSee Less

Comment on Facebook

Street pads too - she won’t have had a hard life mate. 👍

Nice purchase bud.. 🤙🏻

Looks a tidy bit of kit

Looks tidy mate 👍👍

Thoroughly enjoyed my first week for Pope Plant LTD 👍

View more comments

Monday April 15th, 2024
Pope Plant LTD
We are hiring!!
Looking for an excavator operator for a site in Surrey
Must have CPCS or Npors
Own transport to site
Working alongside other 21t excavators and ADT’s of ours on soil treatment facility 
Start date Mon 22nd April for the right candidate 
Message me for more details if interested or email
craig@popeplant.co.uk

We are hiring!!
Looking for an excavator operator for a site in Surrey
Must have CPCS or Npors
Own transport to site
Working alongside other 21t excavators and ADT’s of ours on soil treatment facility
Start date Mon 22nd April for the right candidate
Message me for more details if interested or email
craig@popeplant.co.uk
... See MoreSee Less