RESTORATION WORKS

Pope Plant Ltd was appointed the principal contractor for restoration works at Reigate, based on previous works of a similar nature at Wrotham quarry earlier in the year.

 The works involved the careful planning with particular attention applied to the RAMS to come up with a suitable safe method of works on the upper perimeter track around the quarry.

The pumping system to de-water the site had already been de-commissioned allowing the quarry to flood. The water had risen to such a level as to nearly cut off the access route for plant, this was due to a delay in the awarding of the works. Pope Plant Ltd had to spend an additional 2 weeks carefully placing a sand buttress under the water to try and stabilise the access route. Once partially stabilised, a temporary bailey bridge had to be put into place to allow the trafficking of demolition contractor’s plant to de-commission the conveyors and plant buildings.

Pope Plant Ltd had to work on tight timescales to complete the restoration works involving shaping and top soiling bunds before the water within the quarry rose too much.

Demolition and restoration contract was completed without a day to spare and the bailey bridge was removed in emergency before being submerged under water.

Pope Plant Ltd carried out the works to the satisfaction of Hanson’s and the landowner to within budget including all the additional works.

A new pumping system has now been installed to hold the water at the current level whilst further surveys are completed due to excessive erosion of the sand quarry face.

Further works may be required upon the geologist reports in 2015.

 

“Pope Plant Ltd had to work on tight timescales to complete the restoration works involving shaping and top soiling bunds before the water within the quarry rose too much.”


                  

HANSON-REIG-M-UTTLEY 2017

 

“I would not hesitate to invite Pope Plant ltd to bid for future earthworks projects with Hanson, and
recommend them to any prospective clients.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track pads👍

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track pads👍
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job 👍

Lovely job looking good 💪💪👍

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less

Thursday April 25th, 2024
Pope Plant LTD
Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.

Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.
... See MoreSee Less

Comment on Facebook

Street pads too - she won’t have had a hard life mate. 👍

Nice purchase bud.. 🤙🏻

Looks a tidy bit of kit

Looks tidy mate 👍👍

Thoroughly enjoyed my first week for Pope Plant LTD 👍

View more comments