Temporary Surface Water Management Scheme

After pricing a large scale Surface Water scheme at Seale Lodge for Suez in 2015, which was put on hold due to some design issues, Pope Plant Ltd were asked to construct a temporary scheme to satisfy the local planning authority.

The works involved constructing a GCL lined cut off ditch to stop water existing the site at the main entrance.

A large soakaway was excavated on the site boundary to capture the water from the new cut off ditch.

Aggregate weirs were installed on the main haul road and directed to grass restored areas to prevent water run off.

The works were completed as temporary solution whilst further design work is undertaken by Suez.

 

“The works involved constructing a GCL lined cut off ditch to stop water existing the site at the main entrance.”

Description of the image

SITA-E-FARR 2015

“The success of the project was mainly down to the way Craig Pope and his colleagues understood the client’s needs, worked with an excellent spirit of collaboration and interfaced with all the parties to complete the project.
I would recommend others to seriously consider the services of Pope Plant”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Tuesday May 7th, 2024
Pope Plant LTD
We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details 
craig@popeplant.co.uk

We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details
craig@popeplant.co.uk
... See MoreSee Less

Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track padsđź‘Ť

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track padsđź‘Ť
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job đź‘Ť

Lovely job looking good đź’Şđź’Şđź‘Ť

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less