PHASED CAPPING

Redhill Landfill Southern Area Phased Capping involved the excavation of approximately 110’000m3 of existing membrane capping and soils on a phase by phase basis.

The soils were hauled and placed to temporary stockpiles for later use within the works. The old membrane cap was disposed of to the active landfill.

The client then filled the newly created void with waste from various sources. Upon completetion of filling the area was then made available for re-capping.

Preparation of waste formation was required to receive waste regulation layer. Once regulation material was placed a 0.5mm LLDPE membrane was installed using the lap and lay method. A Geotextile was then placed over the membrane for protection. Conformance testing was completed by a UKAS accredited laboratory.

When the permanent capping was complete, soils were then excavated, hauled and placed to a depth of 1 metre to restore the area.

Finally a surface water management system was installed.

“The old membrane cap was disposed of to the active landfill”


                  

BWSL-A-COLEMAN 2011

 

“Any future employer of this company will soon come to note their commitment and ability to complete a project within budget and without undue compensation events.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Tuesday May 7th, 2024
Pope Plant LTD
We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details 
craig@popeplant.co.uk

We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details
craig@popeplant.co.uk
... See MoreSee Less

Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track pads👍

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track pads👍
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job 👍

Lovely job looking good 💪💪👍

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less