CAPPING AND SURFACE WATER WORKS

On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.

Whilst Biffa was behind with the input of waste to NE quadrant, it was decided by all parties that the work to construct surface water lagoon would begin then follow on to the capping works later upon completion of filling operation.

There was 25’000m3 of clay excavated, hauled and placed on a long haul from one side of site to the other to construct lagoon. This was removed from previously placed stockpile in the rented farmer’s field.

The lagoon was 95% complete only, due to the discharge point to Combe Haven not being granted permission in time by the EA.

Waste filling to NE Quadrant was complete mid November, some 8 weeks behind schedule due to unforeseen reduced inputs. This led to only 8’000m2 of LLDPE welded membrane being deployed by Pope Plant nominated sub-contractor before the worse winter on record stopped the works.

Pope Plant Ltd are due back to site Spring 2014 to complete the remaining works.

“On behalf of Biffa Waste Services., Pebsham LFS Capping and surface water works was awarded by SLR Consulting Ltd to Pope Plant Ltd under contract NEC option B.”


                  

BIFFA-M-STEPHENSON 2011

 

“I have always found working with Pope Plant to be easy and that they are a dependable contractor with high levels of workmanship.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Tuesday May 7th, 2024
Pope Plant LTD
We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details 
craig@popeplant.co.uk

We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details
craig@popeplant.co.uk
... See MoreSee Less

Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track pads👍

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track pads👍
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job 👍

Lovely job looking good 💪💪👍

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less