CELL PREP OF CELL 8 AND CAPPING WORKS

Pope Plant Ltd was awarded the Cell prep of Cell 8 and capping works at Greatness Landfill in June 2012.

 The capping work consisted of placement and preparation of regulation layer and installing 25’000m2 of GCL. The restoration material was hauled and placed from the new Cell 8 excavation. The material was placed to a 1 metre depth above the capping.

The Cell preparation involved removing all unsuitable engineering material and placing to restoration. When the in-situ clay seam was exposed, this was removed to stockpile for later engineering purposes.

When the formation was achieved and approved by Egniol consultants, the clay was used to engineer the base, batter and inter-cell bunds in two 300mm engineered layers.

There were three concrete pads installed for leachate monitoring purposes before the new cell was signed off to the client so installation of tyre bail leachate blanket could begin. The work was completed on time and budget even with wet conditions at the beginning of the project.

“The Cell preparation involved removing all unsuitable engineering material and placing to restoration.”


                  

CORY-M-HARLING 2011

 

“Pope Plant Ltd are continually asked back to tender as on site issues are dealt with effectively and fairly without any claims being submitted as Craig does NOT work on a claims basis.

The work is always carried out to a high standard on time and budget with a 100% Health and safety record. Furthermore Craig is who we always deal with takes ownership of the work and keeps us informed of issues which re always sorted to the best interest of all concerned.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday May 19th, 2022
Pope Plant LTD
Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed

Busy site today at the Pope HQ with another Unit well on its way with the ground slab being installed ... See MoreSee Less

Comment on Facebook

well done mate great achievement, good on you for needing the extra building. glad your busy

Hi Craig, is dad still about

Saturday March 19th, 2022
Pope Plant LTD
Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between

Been a busy few weeks at Pope Plant Ltd
2 week change on our sister company Aveling Securities Ltd land and all this whilst setting up and starting a new contract for one of our trusted clients in Canterbury, Kent
Even somehow found time to renew my CPCS card in between
... See MoreSee Less

Wednesday February 9th, 2022
Pope Plant LTD
Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced

Getting the electric in ready to power up the gate, intercom and CCTV at our premises now that we have the perimeter palisade fenced ... See MoreSee Less