CELL PREP OF CELL 8 AND CAPPING WORKS

Pope Plant Ltd was awarded the Cell prep of Cell 8 and capping works at Greatness Landfill in June 2012.

 The capping work consisted of placement and preparation of regulation layer and installing 25’000m2 of GCL. The restoration material was hauled and placed from the new Cell 8 excavation. The material was placed to a 1 metre depth above the capping.

The Cell preparation involved removing all unsuitable engineering material and placing to restoration. When the in-situ clay seam was exposed, this was removed to stockpile for later engineering purposes.

When the formation was achieved and approved by Egniol consultants, the clay was used to engineer the base, batter and inter-cell bunds in two 300mm engineered layers.

There were three concrete pads installed for leachate monitoring purposes before the new cell was signed off to the client so installation of tyre bail leachate blanket could begin. The work was completed on time and budget even with wet conditions at the beginning of the project.

“The Cell preparation involved removing all unsuitable engineering material and placing to restoration.”


                  

CORY-M-HARLING 2011

 

“Pope Plant Ltd are continually asked back to tender as on site issues are dealt with effectively and fairly without any claims being submitted as Craig does NOT work on a claims basis.

The work is always carried out to a high standard on time and budget with a 100% Health and safety record. Furthermore Craig is who we always deal with takes ownership of the work and keeps us informed of issues which re always sorted to the best interest of all concerned.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Tuesday May 7th, 2024
Pope Plant LTD
We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details 
craig@popeplant.co.uk

We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details
craig@popeplant.co.uk
... See MoreSee Less

Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track pads👍

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track pads👍
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job 👍

Lovely job looking good 💪💪👍

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less