DOWNLAND - MANOR BARN CONTINUES - 2019
The continuation of engineering at Manor Barn Quarry
Cell 2 Side Wall Lift No.2
Cell 3 Base and Side Wall
Restoration of adjacent field upon removal of stockpile
Works commenced to extend the engineering on site to continue infilling of inert materials.
The works consisted of placing site derived and imported material in layers, rolled and tested to create large void space with the intention of getting through to Spring 2020.
An adjacent field used to stockpile site material when entrance road was constructed was ripped and restored back to farming once all material was used for engineering.
Pope Plant Ltd continue to supply Plant and Labour on a weekly basis for the day to day running of the site
“The project team was led by Craig Pope, who was able to deliver the works professionally, on time and in a cost efficient manner. His hands on approach and clear understanding of the technical challenges meant that he was able to liaise effectively with us and to work competently to any directions he was given.
We have full confidence in Craig and his experienced team and would unreservedly recommend his services to anyone requiring similar works undertaken, particularly if there are technically challenging aspects to it.”