CAPPING AND RESTORATION OF CELL 12,13 AND 14

After carrying out clay capping works on Cell 13 in summer 2011, Pope plant Ltd was appointed principal contractor for the capping and restoration of Cell 12, 13 and 14 at Colnbrook Landfill in April 2012.

The works were carried out in two phases totalling 20 weeks work.

The earthworks in phase 1 involved placement and preparation of 70’000m2 of regulation layer. An engineered clay cap was installed to 25’000m2 under CQA supervision from White Young Green consultants, employed for the project by Biffa Waste Services. The consultant also carried out the conformance testing for the site derived clay material on a subcontractor basis to Pope Plant Ltd. The area was then restored to a 1 metre depth comprising subsoil/topsoil.

Phase 2 of the works involved the drilling of 52 new gas wells and 5 new leachate wells carried out by Magpie drilling on a subcontractor basis to Pope Plant ltd. During the drilling works Pope Plant Ltd installed 45’000m2 of GCL and restored with 1 metre of soils. Upon completion of restoration, PE Pipe Technologies Ltd, subcontracted to Pope Plant carried out connecting the newly drilled well’s to the Biffa gas extraction system.

During the two phases of work, Pope Plant encountered some very wet conditions which made the work tough going. Although the site was totally capped by early Dec 12, some restoration work requires completing by Pope Plant spring 2013.

“Pope Plant encountered some very wet conditions which made the work tough going”


                  

BWSL-A-WHITE 2011

 

“The works were completed ahead of schedule with a small team whom were all very professional, with a very strong focus on Health and Safety it was important to me that all the relevant safety documents were in place, these were presented and supplied in an agreed format on time, good use of PPE from all the staff was also noted through out the works.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less

Thursday April 25th, 2024
Pope Plant LTD
Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.

Another Komatsu 210 incoming to the fleet.
Number 7
A bit earlier in year than previously bought but low houred and no Adblue.
Purchased online without viewing so hope as good as the pictures.
... See MoreSee Less

Comment on Facebook

Street pads too - she won’t have had a hard life mate. 👍

Nice purchase bud.. 🤙🏻

Looks a tidy bit of kit

Looks tidy mate 👍👍

Thoroughly enjoyed my first week for Pope Plant LTD 👍

View more comments

Monday April 15th, 2024
Pope Plant LTD
We are hiring!!
Looking for an excavator operator for a site in Surrey
Must have CPCS or Npors
Own transport to site
Working alongside other 21t excavators and ADT’s of ours on soil treatment facility 
Start date Mon 22nd April for the right candidate 
Message me for more details if interested or email
craig@popeplant.co.uk

We are hiring!!
Looking for an excavator operator for a site in Surrey
Must have CPCS or Npors
Own transport to site
Working alongside other 21t excavators and ADT’s of ours on soil treatment facility
Start date Mon 22nd April for the right candidate
Message me for more details if interested or email
craig@popeplant.co.uk
... See MoreSee Less