Cell 6 extension works

Pope Plant Ltd was awarded the Cell 6 extension works at Bellhouse Landfill in April 2012.

 The work consisted of several items of preparatory work to proposed capping area in order to receive engineering clay from Cell extension.

The work involved

  • removing waste to active area of landfill to find the tie-in to existing clay cap
  • working carefully around gas infrastructure buried within waste and capping.
  • Cell extension consisted of constructing an access ramp on a steep incline of waste with 0.5m cover of excavated ballast reject material from LaFargeTarmac part of the site. The material was hauled by a separate contractor and placed by our Cat D6R LGP dozer.
  • A pumping system was installed around cell base to keep the ingress of water under control before excavation could begin.
  • the removal of U/S material was required to determine solid clay base before excess clay was removed to capping area
  • Remaining clay was stockpiled for re-use as engineering material consisting of four 250mm layers to achieve 1m depth of engineered base
  • Within the base an existing intercell bund was removed with the reworking of clay underneath the footprint to complete the consistency of engineering from active cell 6 to extension area.
  • One concrete monitoring pad was built before Cell extension handed over to Client to begin tyre bail leachate blanket instalment.

Due to the nature of the work and close relationship with the client it was elected by all parties that the contract be carried out on a day work basis with no hidden costs.

The work was completed to a high standard within the given timescale.

 

“A pumping system was installed around cell base to keep the ingress of water under control before excavation could begin.”


                  

CORY-TR-MARTIN 2013

 

“I found Craig and his plant operators very professional.  They carried out our projects to a very high standard, within timescales and budgets.  We had good working relations with Craig’s staff.  The plant is kept to a high standard.”

Find out more about

earthworks

Details

Facebook posts

Comments Box SVG iconsUsed for the like, share, comment, and reaction icons
Tuesday May 7th, 2024
Pope Plant LTD
We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details 
craig@popeplant.co.uk

We are still hiring!!
Last minute let down🤯
Looking for an excavator operator for tomorrow if possible at a soil treatment facility in Surrey
CIS only please apply
Can cover until Monday 13th if tomorrow is too early and before I put the position out to agencies to fill.
Please email me your details
craig@popeplant.co.uk
... See MoreSee Less

Thursday May 2nd, 2024
Pope Plant LTD
Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new  grousers on the track pads👍

Been a bit of a rush preparing this one
Apart from the hand painted counterweight it’s pretty clean
No time to rub down, fill and spray properly as off to work next week.
Full service inc Hepa filters fitted for the soil treatment facility it’s off to next week in Hertfordshire
Street pads came off nicely leaving like new grousers on the track pads👍
... See MoreSee Less

Comment on Facebook

Looks good mate fair play to you and your team

Just to add we didn’t paint counterweight !!

Looks well tidy great job 👍

Lovely job looking good 💪💪👍

Thursday April 25th, 2024
Pope Plant LTD

... See MoreSee Less