Clay Mineral Cap & GCL Capping
Pope Plant Ltd was hired on a day work basis to cap the slopes of the landfill with a clay mineral site derived material.
The works comprised of moving circa 10’000m3 of clay on a long haul under the CQA supervision from Terraconsult Ltd.
The clay was placed in 250mm layers and compacted with vibrating padfoot roller to achieve the required testing specification.
Once the clay stockpiles were exhausted it was the preferred route of Cory’s to install 15’000m2 of GCL capping to the crown of the landfill. The area was regulated and compacted in preparation for installing the GCL. This part of the works was carried out on a price work basis.
“The area was regulated and compacted in preparation for installing the GCL”
“Pope Plant Ltd are continually asked back to tender as on site issues are dealt with effectively and fairly without any claims being submitted as Craig does NOT work on a claims basis.
The work is always carried out to a high standard on time and budget with a 100% Health and safety record. Furthermore Craig is who we always deal with takes ownership of the work and keeps us informed of issues which re always sorted to the best interest of all concerned.”